January 2011
In December, TransCanada PipeLines filed an application with the National Energy Board seeking approval of interim tolls for 2011 for its Canadian Mainline system and its Alberta system. The NEB did not approve the specific interim tolls proposed by TransCanada for the Mainline, deciding instead to make the 2010 tolls interim as of January 1. Although TransCanada's preferred option for interim tolls was rejected by the regulator, the application signals the potential for major change in the way TransCanada determines its Mainline tolls.
For a number of years, decreases in firm contract levels and declining throughput on the TransCanada Mainline have been the main drivers for sharp increases in long-haul tolls. In 2007, a shipper using long-haul capacity to move gas to the Eastern Zone paid about $1.03/GJ. In 2010, that same shipper paid almost $1.64/GJ. TransCanada's interim application indicated that a continuation of the status quo would produce a toll to the Eastern Zone of approximately $2.91/GJ. Business factors contributing to the reduction in throughput include new sources of supply available to markets traditionally served by the Mainline, declines in production from the Western Canadian basin, and the impact of the recession in the last two years on natural gas demand.
TransCanada and its stakeholders have been discussing measures for controlling rising long-haul tolls and improving the competitiveness of the Mainline. TransCanada's interim application presented a proposed 3-year agreement that was supported by only some of TransCanada's stakeholders. Elements of the multi-year plan represent a significant departure from established tolling methodologies. TransCanada had hoped to have the tolls resulting from the agreement go into effect on an interim basis while an application for final tolls, also based on the agreement, was being examined by the National Energy Board. Although this was not the outcome, the components of the interim filing provide information on the types and direction of the changes that are being put forward. Highlights of some of the more significant elements that were proposed are:
There are many very specific, detailed components to the proposed agreement. The table below is intended to illustrate representative impacts on TransCanada Mainline tolls. The general direction of tolls under the proposed agreement compared to tolls for 2010 would see long-haul tolls decreasing and short-haul tolls increasing.
|
100% Load Factor Tolls ($/GJ) |
||
Long-Haul Eastern Zone |
Short-Haul Dawn to Union EDA** |
Short-Haul Dawn to Enbridge CDA** |
|
2010 Final | 1.6381 | 0.3168 | 0.1860 |
Proposed Interim 2011 per Agreement | 1.35440 * | 0.3703 | 0.2589 |
2011 per Existing Toll Design as Filed Dec ‘10 | 2.9055 | 0.5703 | 0.3320 |
Reflects Empress to Enbridge CDA since Eastern Toll Zone to be eliminated under proposed plan
* Excludes Union Dawn Receipt Point Surcharge
On January 25, TransCanada filed an application for revised interim tolls for 2011. The revised application is based on the tolling methodology established in the 2007-2011 settlement between TransCanada and its customers, but with updated costs. The proposed Eastern Zone toll is $2.24/GJ.
TransCanada must still file for final tolls for 2011. Whether that application is exactly the same as the first interim filing or a modified version of it as a result of continued discussions with stakeholders remains to be seen. What seems reasonably certain is that there will be a new approach proposed for managing costs, allocating costs, and designing long-haul and short-haul tolls for the Mainline.
Transportation Deserves Attention as Strategy to Control Energy Costs Read more »